We are pleased to inform you that the second stage of the Miasteczko Wawer investment is in progress. Works currently taking place include:
- Bricklaying of TAB internal walls (floor +6, staircase “B")
- Masonry partition walls from blocks of the Multigips type (storey +6, +7 - staircase "B"
- Continuation of mineral wool thermal insulation installation in public areas: staircases, garage +1
- Continuation of sanitary installation works
- Continued installation of domestic ventilation
- Installation of the internal electrical installation in residential premises on floors +5, +6, +7 (staircases "A" and "B")
- Continuation of cosmetic and bottom plate repair works
- Installation of window frames for eastern and western facades (floor +8)
- Plastering walls (storey +1, +5 in staircase "A" and storey +1, +4 in staircase "B")
- Continuation of facade works (southern and eastern facade of the staircase "B")
- Commencement of facade works (west facade)
- Continuation of works on the fire protection tank
- Continuation of works in the field of external rainwater and sanitary installations, sewage, water and sewage connections
- Cosmetic works of reinforced concrete structure
- Installation of steel structure cladding made of T55 trapezoidal metal sheet in the technological holes in the ceiling above the +8 floor (at floor level +9)
- Continuation of the roof waterproofing installation
- Continuation of waterproofing the patio and terrace from the west
- Preparation of elevator shafts in accordance with KONE requirements (painting)
- Beginning of central heating installation works. in residential premises