Foundation piles with caps were implemented for both halls in A and B stages.Assembly works of steel structures in warehouse hall on stage A were initiated.Assembly works of prefabricated station in hall are on stage B.Installation works in main water infrastructures, such as rainwater drainage and hydrant systems are completed.Pavement works were initiated.Concrete block assembly works in the area of pallet shelter no 11 are ongoing.Continuous footings of the transformer station were constructed and masonry works have begun.